Greater Cambridge Local Plan: Proposed Submission

Search representations

Results for Network Rail search

New search New search

Comment

Greater Cambridge Local Plan: Proposed Submission

Policy S/AMC/WHD: Whittlesford Parkway Station Area, Whittlesford Bridge Area of Major Change

Representation ID: 214541

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR and GA welcome the policy’s emphasis on delivering improvements to accessibility and facilities at Whittlesford Parkway Station, as well as the aspiration to create a multi-modal mobility hub.

NR and GA are pleased that GCSP has considered the previous feedback, and that Part 2 (b. i) of this policy has now been amended to include reference to step-free access.

NR and GA are supportive of the proposed allocation and strongly encourage GCSP to engage with us at an early stage to discuss the proposed masterplan, including its objectives, phasing, and funding arrangements.

Comment

Greater Cambridge Local Plan: Proposed Submission

Policy S/AMC/NEC: North East Cambridge Area of Major Change

Representation ID: 214542

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR’s response to Policy S/AMC/NEC focuses on operational railway and infrastructure requirements and should be read alongside the separate submission from Bidwells on behalf of the Chesterton Partnership. NR highlights the importance of its proposed new Maintenance Delivery Unit (MDU) at Chesterton Sidings, which would consolidate maintenance operations and support future rail growth, including East West Rail.

While welcoming amendments made to Figure 38, NR seeks further changes to accurately represent safeguarded rail sidings and emphasises that the figure should be illustrative. It also requests replacing “Aggregates Railhead” with “Railhead”, supports the Agent of Change principle, and stresses the need for early engagement on proposals affecting access to Cambridge North Station.

Comment

Greater Cambridge Local Plan: Proposed Submission

Policy I/ST: Sustainable transport and connectivity

Representation ID: 214543

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

The strategic priorities relating to infrastructure provide clear direction on the importance of sustainable transport. They also set out the expectation that development will be required to contribute towards the delivery of transport schemes necessary to mitigate its impacts.

This approach is reinforced by Policy I/ST (Sustainable Transport and Connectivity), which advises that direct improvements and commitments to transport infrastructure will be secured through planning conditions and/or contributions through planning obligations, community infrastructure levy or its successor.

Network Rail looks forward to working collaboratively with GCSP/developers to ensure that the rail infrastructure improvements required to support growth and delivered.

Support

Greater Cambridge Local Plan: Proposed Submission

Policy I/SI: Safeguarding important infrastructure

Representation ID: 214544

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

Network Rail supports Policy I/SI’s safeguarding of land required for the delivery of East West Rail and welcomes the recognition of safeguarding directions on the Policies Map.

However, the safeguarding provisions do not prejudice or constrain the day-to-day operation of the existing railway. Nor should it limit NR’s ability to maintain, operate, and upgrade the railway and its associated infrastructure within the safeguarded area as required to ensure the safe and efficient operation of the network.

Network Rail welcomes amendments made to Policy I/SI, Part 4, which reflect previous consultation feedback and the status of rail freight sites in Cambridge.

Comment

Greater Cambridge Local Plan: Proposed Submission

Policy I/ID: Infrastructure and delivery

Representation ID: 214547

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR considers it essential that new development contributes, where necessary and justified, towards improvements to railway infrastructure, stations and associated facilities where such measures are required to make development acceptable in planning terms. The cumulative growth planned across Greater Cambridge will place additional demands on the rail network and station infrastructure, and it is therefore important that the draft Local Plan provides an effective mechanism for securing appropriate mitigation and enhancement measures.


NR is committed to working proactively with the GCSP, developers and other stakeholders to identify the need for rail-related infrastructure improvements at an early stage.

Support

Greater Cambridge Local Plan: Proposed Submission

Policy S/C/LCR: Land at Clifton Road (including Cambridge Junction and Cambridge Leisure)

Representation ID: 214550

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR strongly supports the strategic objectives and delivery of East West Rail and is committed to working collaboratively with East West Railway Company (EWR Co) to deliver a high-performing railway that benefits passengers, freight users and taxpayers. NR has engaged with EWR Co on the Regulation 19 consultation and supports EWR Co’s representations relating to the proposed eastern entrance to Cambridge Station, Cambridge East Station, the Beehive Centre Area of Major Change, and associated allocation sites.

Support

Greater Cambridge Local Plan: Proposed Submission

Policy S/CE: Cambridge East

Representation ID: 214552

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR strongly supports the strategic objectives and delivery of East West Rail and is committed to working collaboratively with East West Railway Company (EWR Co) to deliver a high-performing railway that benefits passengers, freight users and taxpayers. NR has engaged with EWR Co on the Regulation 19 consultation and supports EWR Co’s representations relating to the proposed eastern entrance to Cambridge Station, Cambridge East Station, the Beehive Centre Area of Major Change, and associated allocation sites.

Support

Greater Cambridge Local Plan: Proposed Submission

Policy S/AMC/SCL: South of Coldham’s Lane Area of Major Change

Representation ID: 214553

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR strongly supports the strategic objectives and delivery of East West Rail and is committed to working collaboratively with East West Railway Company (EWR Co) to deliver a high-performing railway that benefits passengers, freight users and taxpayers. NR has engaged with EWR Co on the Regulation 19 consultation and supports EWR Co’s representations relating to the proposed eastern entrance to Cambridge Station, Cambridge East Station, the Beehive Centre Area of Major Change, and associated allocation sites.

Support

Greater Cambridge Local Plan: Proposed Submission

Policy S/AMC/BC: Beehive Centre Area of Major Change

Representation ID: 214554

Received: 24/09/2026

Respondent: Network Rail

Representation Summary:

NR strongly supports the strategic objectives and delivery of East West Rail and is committed to working collaboratively with East West Railway Company (EWR Co) to deliver a high-performing railway that benefits passengers, freight users and taxpayers. NR has engaged with EWR Co on the Regulation 19 consultation and supports EWR Co’s representations relating to the proposed eastern entrance to Cambridge Station, Cambridge East Station, the Beehive Centre Area of Major Change, and associated allocation sites.