Policy CC/CE states that developments should be supported by a Construction Environmental Management Plan, which should include an outline of the approach to site waste management and how construction waste will be addressed following a waste hierarchy.
It should be acknowledged that CEMPs are usually prepared at a detailed design stage when the site layout is secured. This will need to be recognised appropriately through the future Policy wording to ensure that the future Policy is effective.
Policy CC/CE states that developments should be supported by a Construction Environmental Management Plan, which should include an outline of the approach to site waste management and how construction waste will be addressed following a waste hierarchy.
It should be acknowledged that CEMPs are usually prepared at a detailed design stage when the site layout is secured. This will need to be recognised appropriately through the future Policy wording to ensure that the future Policy is effective.