Comment
Greater Cambridge Local Plan Preferred Options
Representation ID: 57321
Received: 10/12/2021
Respondent: Huntingdonshire District Council
Careful consideration will have to be given to the timing of delivery in relation to the relocation of the WasteWater Treatment Works and whether this will slow delivery on site.
Huntingdonshire District Council would like assurance that the Councils have additional sites to meet their housing need if delivery slows as a result of the relocation of the WasteWater Treatment Works to ensure that additional demands are not placed on the wider housing market due to under delivery within Greater Cambridge.
Huntingdonshire District Council’s response to the North East Cambridge Development was submitted as part of the North East Cambridge Area Action Plan consultations.
Careful consideration will have to be given to the timing of delivery in relation to the relocation of the WasteWater Treatment Works and whether this will slow delivery on site.
Huntingdonshire District Council would like assurance that the Councils have additional sites to meet their housing need if delivery slows as a result of the relocation of the WasteWater Treatment Works to ensure that additional demands are not placed on the wider housing market due to under delivery within Greater Cambridge.