Cambridge East - Land north of Newmarket Road
Although an outline consent has been issued, there remains the first Reserved Matters to be resolved. Additionally, the Section 106 provides explicit requirements for the delivery of the first wave of housing by November 2020. As such, the trajectory where it identifies delivery from 2020/2021 reflects this requirement, but the quantum established of 110 dwellings seems overly optimistic. A reduction in this quantum for the first wave of delivery, or an appropriate re-attribution of numbers across a longer period would be a practical option which would allow for a greater extent of flexibility in the case of a delay in implementation or unforeseen increase in delivered numbers.