Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document
Representation ID: 168448
Received: 14/10/2019
Respondent: Gladman Developments
Representation Summary:
Cambourne West
It is critical that the delivery rates and lead-in times associated with sites in the supply are realistic and achievable. Gladman are concerned regarding the lead-in times of a number of sites, in particular on the basis of the time assumed for gaining planning consent.
Within South Cambridgeshire, our concerns regarding lead-in times relate primarily to three large sites (Waterbeach New Town, Bourn Airfield New Village and Cambourne West) where the anticipated delivery by the Council is considered overly optimistic given that in two cases outline consent has not yet been granted.