Success
Information
Error
Greater Cambridge Local Plan: Proposed Submission
Search representations
Results for Quy Tech Ltd on behalf of landowners search
New searchNew searchObject
Greater Cambridge Local Plan: Proposed Submission
Chapter 2: Development strategy
Representation ID: 213319
Received: 25/09/2026
Respondent: Quy Tech Ltd on behalf of landowners
Agent: Carter Jonas
Legally compliant? Yes
Sound? No
This representation relates to a site submission (HELAA ref 208854 Quy Tech, Land to the north of the A14, Stow cum Quy, CB239AF)
Quy Tech Ltd are promoting a 165-hectare site in Stow-cum-Quy, northeast of Cambridge, named ‘Quy Tech’, for a mid-tech employment campus. This development would provide modern employment space, tailored housing for workers, and complementary facilities, all powered by an on-site solar farm. I am concerned that the current Greater Cambridge Local Plan does not reflect the area’s potential or government objectives, as it fails to allocate enough sites for employment growth. The plan should embrace innovative, multi-faceted proposals like Quy Tech to attract global research and innovation operators.
We strongly urge Greater Cambridge to look again at the evidence which underpins the economic strategy and to positively plan for more economic development growth, especially to the east of Cambridge to complement and serve the new development already coming forward in the area.
Quy Tech Ltd, are promoting a 165 hectare site in Stow-cum-Quy, to the north east of Cambridge, for a potential employment land allocation to comprise a campus based mid-tech employment facility. The site is referred to as ‘Quy Tech’ for the purpose of these representations.
The Site is promoted for the development of a campus based mid-tech employment facility, not only to provide important contemporary employment floorspace but bespoke ancillary housing needed to serve the employment uses and additional complementary facilities. All with the wider ability to be self-powered by the site’s own solar farm.
As set out in the representations previously submitted to the Reg 18 consultation, we are extremely concerned that the needs identified in the evidence base to the Greater Cambridge Local Plan do not reflect Cambridge’s potential, are not sufficiently ambitious and do not match up to Government objectives for the area. Too few sites are allocated for employment development, and it is disappointing in this respect that the potential identified for Quy Tech has not been considered further through the Local Plan process.
This Greater Cambridge Local Plan vision requires upbeat economic forecasts. Rather than simply being anchored in historic trends therefore, there is a need for Greater Cambridge to embrace, through the Local Plan process, innovation and multi-faceted campus proposals such as Quy Tech, able to provide employment floorspace alongside bespoke residential proposals and wider ancillary facilities in a self-powered campus and in doing so be able to attract global operators in research and innovation.
Object
Greater Cambridge Local Plan: Proposed Submission
Policy S/JH: New jobs and homes
Representation ID: 213358
Received: 25/09/2026
Respondent: Quy Tech Ltd on behalf of landowners
Agent: Carter Jonas
Legally compliant? Yes
Sound? No
Quy Tech Ltd object to Policy S/JH. The policy is overly conservative, lacks justification, and fails to align with national planning policies or the region's growth aspirations. Quy Tech Ltd proposes a 165-hectare employment site with mid-tech facilities, ancillary housing, and solar-powered infrastructure, complementing existing developments like Cambridge East. The employment land assessment remains unchanged, ignoring the need for campus-based mid-tech facilities or strengthening employment in East Cambridge. The policy assumes a lower job growth scenario, contradicting recent economic trends and government ambitions for Cambridge's expansion. The plan should reflect higher growth targets to support innovation and infrastructure-led development.
The following changes to Policy S/JH are requested.
We strongly urge Greater Cambridge to look again at the evidence which underpins the economic strategy and to positively plan for more economic development growth, especially to the East of Cambridge to complement and serve the new development already coming forward in the area.
Specifically, it is requested that:
• The employment target is recalculated having regard to ‘higher’ growth scenarios that better reflect the clear national objectives for Cambridge.
• The need for additional employment growth to the east of Cambridge to align with growth aspirations for this part of the City is acknowledged and considered further.
• Identification of a need for a ‘new mixed industrial / tech park’ preferably located on the Cambridge fringe is considered further in the context of a higher growth scenario, as sought above, and is updated accordingly to confirm need for a new campus based mid-tech employment facility in Greater Cambridge.
• ‘Quy Tech’ is revisited as a deliverable, viable opportunity to meet all of the above needs.
NOT SOUND – NOT JUSTIFIED, NOT EFFECTIVE, DOES NOT ALIGN WITH ASPIRATIONS FOR THE REGION, NOT CONSISTENT WITH NATIONAL PLANNING POLICY.
OBJECT :
These representations are submitted by Quy Tech Ltd, on behalf of the landowners, and are made with reference to a potential employment land allocation at Quy Tech (The Site), a 165-ha site in Stow-cum-Quy.
We strongly object to Policy S/JH: New Jobs and Homes. Further to representations submitted to the Regulation 18 draft Local Plan the approach taken remains unduly conservative with no justification provided for the adopted rationale.
The Site is promoted for the development of a campus based mid-tech employment facility, not only to provide important contemporary employment floorspace but bespoke ancillary housing needed to serve the employment uses and additional complementary facilities. All with the wider ability to be self-powered by the site’s own solar farm.
Having regard to representations made to the Reg 18 draft Greater Cambridge Local Plan, including representations from Quy Tech Ltd. The Council has confirmed that:
The Councils consider that the draft plan vision and strategic priorities remain appropriate and have not made amendments in response to representations made at draft plan stage, noting that amendments were made at draft plan stage to add greater emphasis on supporting the economy, that both the vision and strategic priorities already reference our locally distinctive heritage and landscapes and unique character and identities of Cambridge and South Cambridgeshire. Whilst we acknowledge the importance of greenspaces for wellbeing, green spaces provide cross cutting benefits relevant to a number of the strategic priorities. The strategic priorities should be understood collectively; the Councils consider that it would reduce the clarity of the priorities to make cross-references between them. Adding references to specific services such as emergency services is considered too detailed for these strategic level priorities.
Whilst choices made to inform the preferred development strategy inevitably require a balancing between issues included within the vision and strategic priorities, the vision and priorities have informed the development strategy principles and thereby the strategy itself. The Councils therefore consider that the development strategy is aligned with the vision and strategic priorities.
In terms of additional work undertaken since the Reg 18 consultation no new employment land assessment has been provided. Instead, Iceni Projects, authors of the Greater Cambridge Employment and Housing Needs Update 2024-2045 published in 2025, have been asked to review the robustness of the latest Greater Cambridge Local Plan evidence in relation to employment and housing needs having regard to the latest available data and representations to the Regulation 18 Plan. In this context Iceni Projects has concluded as follows:
“Iceni has reviewed the representations made across a range of topics and consider the evidenced position in the EHNU 2025 and predecessor reports to remain robust.”
It is in this context that Greater Cambridge propose no fundamental amendments to Policy S/JH: New Jobs and Homes. Accordingly, the basis for our continued objection is reaffirmed below:
East Cambridge is a clear direction of travel for growth in Greater Cambridge. The failure to recognise the east of Cambridge as a wider gateway opportunity, with the necessary infrastructure and connectivity already in place, to sustain greater levels of economic and residential growth represents a wasted opportunity.
Quy Tech is just 250m north of the Cambridge East allocation and ideally located to connect into and complement the new development at Marleigh and development of East Cambridge at Cambridge Airport. In terms of wider connectivity, the Site has direct access to the A14, whilst the Cambridge East development, Newmarket Road travel hub and Cambridge North are all directly accessible from the Site by standalone foot and cycle routes.
An Economic Assessment was submitted, on behalf of Quy Tech Ltd, to the Regulation 18 draft Local Plan. It is submitted again in response to the Reg 19 draft for completeness. This piece of work assesses the economic aspirations of the draft Greater Cambridge Local Plan. It concludes that:
• The need for employment, and especially knowledge-intensive employment, is much greater than that identified and allocated for in the draft Local Plan.
• The identified needs do not reflect new and emerging trends.
• The conclusions drawn are primarily quantitative i.e. simple floorspace figures, without qualitative assessment of the location, nature and setting of accommodation needed. Fundamentally, this work fails to recognise the growing need for campus based contemporary commercial floorspace.
Having regard to representations suggesting ‘underestimation of need for mid-tech, data centres and agri-tech space’ Iceni have restated the robustness of the 2024 Greater Cambridge Warehouse and Industrial Space Needs Study in their 2026 review. The 2024 study recommends “A new mixed industrial / tech park on the SRN [strategic road network], preferably but not critically located on the Cambridge fringe”. Iceni consider that this remains a suitable recommendation. It remains unclear however why ‘Quy-Tech’ is not considered well placed to address this need.
It is highly notable that nowhere in the updated evidence base for the Reg 19 draft Local Plan is the need for the development of a campus based mid-tech employment facility considered, nor the need to strengthen employment provision to the east of Cambridge to complement and connect into the wider growth aspirations.
A Vision Document for the site (originally submitted to the Reg 18 draft Local Plan) is again hereby submitted for completeness to accompany these representations. The document sets out how proposals for the Site can come forward and the strength of connectivity to the Cambridge East development i.e. Marleigh and the proposals for the airport, the nearby Newmarket Road Travel Hub and Cambridge North train station.
The Site is recommended for allocation in the Greater Cambridge Local Plan on this basis.
Draft policy S/JH continues, as it did in the Reg 18 draft, to identify therefore a need for 73,300 additional jobs over the period 2024-2045. Need is specifically identified for:
• 302,600 sqm offices and 600,000 sqm of Research and Development (R&D) space
• 317,000 sqm of industrial / warehousing (use classes B2/B8).
The Employment and Housing Evidence Update 2025 (EHEU), which informs the Draft Greater Cambridge Local Plan, assumes a ‘central’ rather than a ‘high’ jobs growth scenario, in effect downgrading growth to a lower longer term growth trend (the last 20 years) rather than the higher rate of growth seen in Greater Cambridge over the last 10 years. The EHEU assumes that this is the most realistic scenario on the basis of the anticipated housing delivery. A full assessment of the EHEU is provided in the accompanying Economic Assessment.
It is notable that at paragraph 3.62 the EHEU states:
“It is important to acknowledge that the high scenario could be achieved or exceeded. For this to take place it is considered that a step change in infrastructure investment and development would be needed to facilitate growth…”
Within the 2026 update of this work provided by Iceni Projects to inform the Reg 19 draft they confirm that the adopted scenarios are “considered realistic and embedded in past trends for known change, including periods of strong growth, but also taking into account periods of cyclical slow down…” This position remains unchanged therefore and it is on this basis that the predictions of need, as detailed above, remain as per the Reg 18 draft policies.
The NPPF was revised in 2026. It continues to provide strong support for economic growth and the delivery of high-tech development. The revised Framework places greater emphasis on “unlocking economic growth”, supporting key economic sectors, and ensuring that planning positively meets development needs. It also promotes infrastructure-led growth, innovation, and the provision of employment land needed to support nationally important sectors, including science, technology, research and development, advanced manufacturing and data-driven industries. The August 2026 NPPF clearly provides a supportive backdrop to allocating and approving high-value employment land at Quy Tech, where it can support innovation, knowledge-intensive businesses, productivity growth and associated infrastructure delivery to the east of Cambridge.
In 2024 the Government established the Cambridge Growth Company with the driving goal to maximise Cambridge’s full economic potential and to deliver nationally significant growth. The Growth Company specifically aims to unlock and accelerate development for Cambridge, and to deliver the homes, jobs and infrastructure needed for the long-term and sustainable growth of the City. Further to this, the Government recently announced, 23rd October 2025, a £400 million investment in Cambridge to help facilitate the delivery of affordable homes, infrastructure and business expansion.
Building on this, the Greater Cambridge Development Corporation was subsequently established by Government in July 2026 to unlock and accelerate development for Cambridge, and to deliver the homes, jobs and infrastructure needed for the long-term and sustainable growth of the City. It will seek to tackle barriers to growth, such as water and transport infrastructure and traffic congestion to deliver ambitious levels of growth.
Whilst it is acknowledged that the draft GCLP does not necessarily need to take into account the levels of growth to be addressed by the Development Corporation, it is tangible evidence of growth ambitions for Cambridge that should be appropriately reflected in the draft GCLP and its evidence base. Contrary to this, the Iceni 2026 update instead considers the Government’s increased level of commitment remains largely aspirational with details yet to be fully clarified. As such they considered that national aims for Cambridge should not be reflected in the Local Plan evidence base, which is based wholly on evidenced sector and economy wide performance. To ignore this wider context seems somewhat perverse and to fly in the face of the Local Plan process which the 2026 NPPF reaffirms should ‘set a positive vision for future growth and change at a sub-regional scale and provide a clear spatial framework for investment and growth…’.
There are a number of proposed and planned infrastructure projects in Greater Cambridge that should have been taken into account in deciding whether adjustments should be made to the targets in Policy S/JH. The list of infrastructure projects includes East West Rail, Cambourne to Cambridge Busway, Cambridge South East Transport project, Waterbeach to Cambridge Busway, Cambridge Eastern Access project, and Cambridge South Station. In addition, the Greater Cambridge Partnership is delivering greenways to connect surrounding villages to Cambridge by walking and cycling. The funding for some of these projects has not been confirmed, but it is anticipated that they will need to be supported by associated development.
It remains unclear in this context therefore why the draft Cambridge Local Plan would assume impediment to the higher growth scenarios and adopt a more conservative ‘central’ scenario. As a result, opportunities, such as the continued growth of East Cambridge are being lost.
It is worthy of note that the conclusions of the EHEU are caveated as being conservative, and at page 19 of the report it is explained that:
“The [Centre for Business Research] CBR data presents a more positive picture of economic growth for recent years than the adjusted [Business Register and Employment Survey] BRES data. The BRES data indicates compound annual growth rate (CAGR) for employment in Greater Cambridge of 1.4% between 2020 and 2023. By contrast, CBR’s analysis suggests that overall employment grew by 2.5% in 2020-21, 6.7% in 2021- 22, 6.3% in 2022-23, and 5.3% in 2023-24. This amounts to a CAGR from 2020-21 to 2022-23 of 5.1%.
CBR’s data also provides a more positive view of growth in key sectors in Greater Cambridge. The CBR data suggests that knowledge-intensive (KI) employment has been strong, with growth of 5.8%, 7.8% and 11.2% in 2020-21, 2021-22 and 2022-23 respectively.”
In the EHEU report it is argued that the CBR data confirms that it would not be appropriate to revise growth forecasts downwards (which latest BRES might suggest). The CBR data would instead lean towards a conclusion of planning for a high level of employment growth, and yet that higher growth scenario is not the one planned for in the emerging Local Plan.
It is also evident that even the EHEU “High figure” is below the 10-year historic growth rate and there is potential for greater alignment to 20-year growth ambitions, which would be more appropriate for a nationally, and globally important economic ecosystem such as that in Cambridge.
The “Greater Cambridge: Growth Scenarios” research published by Government in November 2025 identifies that additional activity in knowledge intensive sectors and housing delivery could enable a substantial increase in employment. Over and above that identified by the draft Local Plan.
The growth scenarios modelled in this research suggest that Greater Cambridge could support a total of 380,000 to 465,000 jobs by 2050. This represents between a 60% and 100% increase in the size of the existing Greater Cambridge workforce (236,000 jobs) and would see employment growth around 20% to 45% higher than is assumed the baseline forecast (321,000 jobs) of the draft Local Plan.
Whilst these scenarios stretch as far as 2050 it is clear that these figures are significantly higher than the 73,300 new jobs envisaged by the draft Greater Cambridge Local Plan.
We are extremely concerned that the needs identified in the evidence base to the Greater Cambridge Local Plan do not reflect Cambridge’s potential, are not sufficiently ambitious and do not match up to Government objectives for the area. Too few sites are allocated for employment development.
The Government’s aims for Cambridge are ambitious whilst the vision for the Local Plan distinctly seeks to ‘encourage a flourishing, dynamic and mixed economy in Greater Cambridge which includes a wide range of jobs, while maintaining our area's global reputation for education, research and innovation’. There is then a clear disconnect between the strength of these ambitions and detailed policy which is not sufficiently proactive and fails to identify suitable employment sites to deliver the economic development sought. The entirety of the draft Local Plan policy needs to align with Government’s ambitions for Greater Cambridge.
This vision requires upbeat economic forecasts, which rather than simply being anchored in historic trends need to embrace innovation and multi-faceted campus proposals such as Quy Tech, able to provide employment floorspace alongside bespoke residential proposals and wider ancillary facilities in a self-powered campus and in doing so be able to attract global operators in research and innovation.
Object
Greater Cambridge Local Plan: Proposed Submission
Policy S/DS: Development strategy
Representation ID: 213365
Received: 25/09/2026
Respondent: Quy Tech Ltd on behalf of landowners
Agent: Carter Jonas
Legally compliant? Yes
Sound? No
Quy Tech Ltd objects to the draft GCLP Policy S/DS for being too conservative, failing to meet employment needs—especially mid-tech—and ignoring eastern growth opportunities like Quy Tech. The plan lacks qualitative assessment, relies on outdated evidence, and doesn’t allocate enough land for key sectors such as mid-tech or campus-based facilities. Quy Tech could provide self-powered, mixed-use employment and housing, supporting Cambridge’s innovation economy and connectivity to Cambridge East. The plan’s narrow focus on quantitative growth risks missing strategic opportunities. Reconsideration of the evidence base is urged, as is inclusion Quy Tech to align with national and local growth aspirations.
The following changes to Policy S/DS are requested.
We strongly urge Greater Cambridge to look again at the evidence which underpins the economic strategy and to positively plan for more economic development growth, especially to the East of Cambridge to complement and serve the new development already coming forward in the area.
It is recommended that quantative modelling should be aspirational and not based solely on past trends, furthermore it is requested that this is complemented by more bespoke analysis that identifies future need for which data cannot be extracted from past trends, such as the need for a bespoke, campus focus mid tech opportunity.
It is recommended that the land promoted at Quy Tech be identified as suitable for meeting the need for a new campus led employment development, acknowledging the benefit bespoke housing aimed at employment users and ancillary facilities such a development would bring in attracting innovative and global operators to Cambridge and the opportunity development of the site presents in complementing proposed transport infrastructure projects to the east of Cambridge and the potential to facilitate transport benefits over and above this.
It is strongly recommended that the land presented at Quy Tech is formally allocated for bespoke employment generating development.
NOT SOUND – NOT JUSTIFIED, NOT EFFECTIVE, USE OF INAPPROPRIATE EVIDENCE BASE, IS NOT CONSISTENT WITH NATIONAL PLANNING POLICY.
These representations are submitted by Quy Tech Ltd, on behalf of the landowners and are made with reference to a potential employment land allocation at Quy Tech, a 165-ha site in Stow-cum-Quy.
The Site is promoted for the development of a campus based mid-tech facility, not only providing important contemporary employment accommodation but also bespoke complementary housing and ancillary facilities. All with the wider ability to be self-powered by the site’s own solar farm.
These representations are accompanied by an Economic Assessment (hereby submitted) of the economic aspirations of the draft Greater Cambridge Local Plan. This concludes that:
• The need for employment, and especially knowledge-intensive employment, is much greater than that identified and allocated for in the draft Local Plan.
• The identified needs do not reflect new and emerging trends.
• The conclusions drawn are primarily quantitative i.e. simple floorspace figures, without qualitative assessment of the location, nature and setting of accommodation needed. Fundamentally, this work fails to recognise the growing need for campus based contemporary commercial floorspace.
A Vision Document (hereby submitted) for the Site also accompanies these representations. The document sets out how proposals for the Site can come forward and the strength of connectivity to the Cambridge East development i.e. Marleigh and the proposals for the airport, the nearby Newmarket Road Travel Hub and Cambridge North train station.
Quy Tech Ltd continue to recommend Quy Tech for allocation in the Greater Cambridge Local Plan on this basis.
We have objected previously to the employment allocations listed in draft policy S/DS of the Reg 18 Consultation Draft, principally on the basis that the plan was too conservative. This is captured by the Council in their summary of issues arising from representations to the Reg 18 (Appendix 6: Development Strategy, 2026 Consultation Strategy).
“Objection that the strategy is too conservative in identifying insufficient jobs and homes for sustainable growth in Cambridge, does not align with the Government’s growth agenda, and that the housing requirement does not align with jobs growth. Comment that the Plan does not provide enough housing land to meet the needs. Objection that the Plan is not meeting the need for specific sectors including large scale warehousing, mid-tech, agri-tech, and data centres.”
The Council confirm that they have considered comments that the Plan is not meeting the need for specific sectors including warehousing, mid-tech, agri-tech and data centres. Having regard to greater need for mid-tech provision the Council respond as follows:
‘For mid-tech, the Councils’ Industrial and Warehousing Study 2024 explored this topic including engaging with mid-tech occupiers, identifying mixed views. The Proposed Submission Plan includes sufficient allocations in priority locations that meet the needs identified in the study.’
In this context, Quy Tech Ltd are also submitting representations to Policy S/JH: New Jobs and Homes of the Reg 19 draft Greater Cambridge Local Plan making clear continued disappointment that Greater Cambridge has not adopted ‘higher’ growth scenarios that better reflect future growth aspirations for Cambridge and its hinterlands.
Concerns in relation to the Development Strategy as set out at Policy S/DS are reaffirmed below.
The plan is too conservative; the growth rates are not sufficiently ambitious and there is a need to identify additional sites for employment development. This is critical if both Government aspirations for the area, further reaffirmed through the establishment of the Greater Cambridge Development Corporation in July 2026, and Greater Cambridge’s own vision to ‘encourage a flourishing, dynamic and mixed economy in Greater Cambridge which includes a wide range of jobs, while maintaining our area's global reputation for education, research and innovation’ are to be realised.
Policy S/DS confirms that sites on the edge of Cambridge will be prioritised as locations for meeting the need for jobs and homes in Greater Cambridge, outside the Cambridge urban area. Opportunities are not however identified within this hierarchy.
There is a complete failure to recognise the direction of growth towards the east of Cambridge and the opportunity this area presents. Further development to the east offers the potential to build on already committed growth in this area including the allocations at Marleigh and Springstead Village, which are already built out and occupied, to be supplemented further by Cambridge East, with the recent acquisition by Homes England and the Hill Group of land to provide a new community of 10,000+ homes.
The failure to recognise the east of Cambridge as a wider gateway opportunity, with the necessary infrastructure and connectivity in place, to sustain greater levels of economic and residential growth represents a wasted opportunity.
This Site is just 250m north of the Cambridge East allocation and ideally located to connect into and complement the new development at Marleigh and that proposed for Cambridge Airport. In terms of wider connectivity, the Site has direct access to the A14, whilst the Cambridge East development, Newmarket Road travel hub and Cambridge North are all directly accessible from the Site by standalone foot and cycle routes.
Additionally, no site in Greater Cambridge has been identified to provide a new campus-based employment facility able to offer complementary facilities, such as housing targeted to the needs of the employment operators. This represents a lost opportunity. It is unclear how policy aims to meet the Greater Cambridge Vision to maintain Cambridge’s global reputation without such forward thinking, innovative proposals able to tap into contemporary commercial needs.
Need for additional sites:
We are extremely concerned that the economic forecasts of the draft Greater Cambridge Local Plan are not as ambitious as they should be and do not match up to the Governments aspirations for the area. As a result, too few sites are allocated for employment development.
We consider that Greater Cambridge should look again at the evidence which underpins the economic strategy, should adopt more proactive and positive scenarios for growth and should support more economic development on sites such as the opportunity presented at Quy Tech.
East Cambridge:
It is clear that R&D as a sector has a long tradition of growth in and around Cambridge. This growth remains strong and is an important contributor to not only the local and regional economy but also the whole of the UK. It is vital therefore, that the right quantum of new development is identified, but also that it is in the right places, and can support a range of occupiers.
There is a clear shortage of large-scale office, R&D, and mid-tech space in the eastern Cambridge corridor. Industrial and light industrial provision is similarly constrained, with few options for units above 50,000 sq. ft. The Site at Quy Tech represents a development opportunity well located to bring forward high-quality space to meet these unmet needs. An economic assessment accompanies these representations that makes clear this position.
Quy Tech has the benefit of being on the edge of Cambridge and as such being prioritised as a suitable location for growth, outside of the Cambridge built up area. In terms of wider connectivity, the Site has direct access to the A14, whilst the Cambridge East development, Newmarket Road travel hub and Cambridge North are all directly accessible from the Site by standalone foot and cycle routes.
Currently the employment allocations as listed at Policy S/DS: Development Strategy are predominantly to the north (Waterbeach) the North West (off the A14) and the South (Cambridge Bio Medical Campus and Wellcome Genome Campus).
To the east, there are limited employment allocations given the proposed housing growth. Quy Tech is ideally located to support the growth of the existing Cambridge East allocation. Much of the northern phase of the allocation (the Marleigh development) is now built out including the development of foot and cycle ways to connect to Low Fen Drove which directly accesses the Quy Tech Site, approximately 250 m to the north.
Quy Tech offers the unique opportunity therefore to provide a campus led mid-tech employment floorspace that is fully integrated into the wider aspirations for Cambridge East aspirations, as is evidenced in the accompanying Vision Document. This should be recognised through Policy S/DS: Development Strategy.
East Cambridge - Transport Infrastructure;
It is not clear why the draft Local Plan is being informed by an ‘interim’ Cambridge Transport Strategy (June 2026) as opposed to a final piece of work. It is suggested that a final strategy should be prepared that considers, and plans for, ‘higher’ growth economic scenarios.
It confirms, in the medium term (2030-2035) a package of improvements to East Cambridge to include completion of eastern Gateways, relocation of Newmarket Park & Ride to a higher capacity site, and future mass rapid transit to Cambridge East along Newmarket Road. Longer term there are more aspirational targets to provide a Cambridge East train station. The opportunity at Quy Tech aligns with these objectives and has the ability to enhance transport infrastructure to the East of Cambridge further.
The interim Transport Strategy identifies that congestion on major gateways into Cambridge, including via the A14 is ‘constraining access to jobs, education and services, reducing bus reliability, and weakening the quality of place that underpins the city’s international competitiveness’. The Greater Cambridge Transport Strategy Intervention Delivery Plan (Table 5.1) therefore confirms the following:
‘Working with National Highways and local partners, CPCA would support the longer-term development and assessment of potential proposals to improve the performance, resilience and connectivity of the A14 corridor in and around Greater Cambridge’.
Quy Tech is ideally placed to potentially help deliver wider transport infrastructure improvements to the principal transport gateway to the east of Cambridge to the benefit of Cambridge as a whole. It is recommended that this is recognised through Policy S/DS: Development Strategy to allow this opportunity to be explored further.
Campus led mid-tech accommodation:
It is evident that the growth scenarios for establishing need for employment floorspace are derived principally from quantitative modelling. Little regard has been had to the bespoke nature of the accommodation, facilities and locations required by the innovative operators that Greater Cambridge is keen to attract.
The ‘update’ to the EHEU is fundamentally based on a market report from some 6 years ago, in 2020. The draft Greater Cambridge Local Plan is reliant therefore on market trends that are already outdated. Over and above the quantity of development aspired to in the draft Local Plan we have significant concerns that the nature of development sought does not accurately reflect current commercial needs and is not aligned with the vision to ‘encourage a flourishing, dynamic and mixed economy in Greater Cambridge which includes a wide range of jobs, while maintaining our area's global reputation for education, research and innovation’.
Specifically, the EHEU fails to appropriately reflect more recent mid-tech trends such as bespoke office/lab enabled on-site production and distribution, as demanded by newly forming and ‘spin-out’ business in the KI sector. In qualitative terms, there is insufficient consideration, in the EHEU, and Greater Cambridge Local Plan, of the nature and location of property stock likely to be sought by such operators. This position is explored fully in the accompanying Economic Assessment submitted in support of these representations.
Whilst the Wellcome Genome Campus, Hinxton is specifically referenced in the 2020 Employment Land and Economic Development Evidence Study no further work appears to have been done to identify the benefits of campus-based space i.e. the benefit of providing complementary facilities, such as short lease housing for visiting global researchers etc.
It is evident that none of the other employment land allocations identified in the plan specifically target a campus based mid tech offering, able to offer the complementary facilities needed to attract global operators. We object to Policy S/DS: Development Strategy on this basis.
Campuses are crucial for the UK's economy, fostering innovation, driving growth in high-tech sectors (like life sciences, AI, space), creating high-value jobs, attracting investment, and strengthening collaboration between universities, businesses, and government, essentially acting as regional innovation hubs that anchor talent and boost productivity in the knowledge economy.
Campuses are at the forefront of delivering:
• Economic growth and innovation
• Facilitating Collaboration and Knowledge Sharing
• Talent Attraction and Development
• Sustainability and Future-Proofing
• Creating a "Sense of Place"
Quy Tech offers the unique opportunity to create a campus that prioritises mid-tech facilities, requiring adaptable floorplates to cater to hybrid occupiers and the flexibility of office, lab, and light manufacturing capabilities. It is then proposed that the Site can be supplemented by a proportion of office / R&D space with supporting amenities.
It is proposed Quy Tech comprises not only employment accommodation, but bespoke housing able to complement the employment uses i.e. short term leases to attract global researchers, and other wider ancillary facilities demanded by innovative and global operators. Without a new multi-faceted campus facility able to provide this breadth of offer the draft policy simply won’t attract the innovative sectors of the economy it is seeking. Furthermore, Quy Tech offers the opportunity for this new floorspace to be self-powered through an on site solar farm. A completely self-sufficient and sustainable approach to energy requirements.
It requires forward thinking, proactive policy that responds to market demands to provide the necessary conditions to attract future innovative businesses not a reliance simply on past trends and historic economic growth rates. Cambridge East, and namely Quy Tech, provide the perfect environment in which to bring forward the necessary employment multi-faceted campus facility.
The allocation of Quy Tech, focusing on the mid-tech sector will help position the east of Cambridge to attract advanced engineering, technology and life science firms which is currently unable to do. Quy Tech can leverage proximity to the A14 and its access to both Newmarket Road travel hub and Cambridge North Train Station to enhance connectivity credentials whilst ensuring that it aligns with regional economic objectives and complements major allocations such as Northeast Cambridge and Cambridge East.
Additionally, Quy Tech offers real potential to underpin wider growth aspirations to the east of Cambridge with the ability to integrate with, through strong physical linkages, and support both the residential and employment uses to come forward as part of the Cambridge East allocations. In this respect the Site would both help promote and sustain the City’s innovative global reputation whilst also supporting sustainable growth and in so doing respond positively to the development vision as set out through the draft Plan.
The site is referenced as 208854 in the HELAA, following submissions to the Reg 18 draft local plan. There is suggestion that in landscape terms the site would become an urban extension and this is not agreed with. The site would be well screened and largely sat at a lower level to the adjacent A4 which would also ensure the site would remain distinct. It is not clear how issues such as landscape impact, ecology and access can be flagged as ‘red’ without further consideration.
All of these issues need to be balanced against the need for employment growth, in particular a campus based mid-tech, and in this context, it would be anticipated that these are issues to which appropriate technical resolution and mitigation would be required. These issues, of themselves, should not be considered fundamental barriers to the development of the site. It is also notable that the potential benefits of bringing forward the site are not considered alongside the technical issues raised to enable the necessary planning balance to be considered.
To confirm the query ‘It is unknown when the site would be available for development’. The site is promoted on behalf of the landowners. The site is readily available to come forward in a timely manner, therefore.
We object to Policy S/DS: Development Strategy and think it unsound. There is a need to identify additional sites for employment development in Greater Cambridge. Despite the clear direction of growth towards the east of Cambridge, it is underrepresented in terms of allocations as set out at draft Policy S/DS and as such policy fails to build on already committed growth in this area including the allocations at Cambridge East, notably areas such as Marleigh, Cambridge Airport and Springstead Village.
We object to Policy S/DS failure to allocate land for a new campus led employment development and acknowledge the benefit of bespoke housing aimed at employment users and ancillary facilities such a development would bring in attracting innovative and global operators to Cambridge. This represents a significant lost opportunity for the local economy as the plan is currently drafted.
Object
Greater Cambridge Local Plan: Proposed Submission
Policy S/GB: The Cambridge Green Belt
Representation ID: 213392
Received: 25/09/2026
Respondent: Quy Tech Ltd on behalf of landowners
Agent: Carter Jonas
Legally compliant? Yes
Sound? No
Quy Tech Ltd object to draft Policy S/GB. The current policy fails to align with NPPF criteria, particularly in preventing town merging, and overlooks grey belt considerations. The Quy Tech site, promoted for a mid-tech employment campus with solar-powered self-sufficiency, is strategically located near Cambridge East and Marleigh, offering strong connectivity via the A14 and cycle routes. Economic assessments highlight unmet demand for knowledge-intensive employment space, which the draft Local Plan underestimates. While other nearby sites would require significant Green Belt release, Quy Tech’s development would have minimal impact, making it a viable option to meet growth needs.
The following changes to Policy S/GB are requested.
Further green belt release is required to meet additional need for employment floorspace. It is recommended that the removal of the Quy Tech Site from the Green Belt should be considered in this context.
It is suggested that Policy S/GB make clear that the contribution of Green Belt will be considered in the context of national Grey Belt planning policy where an evidenced need can be presented.
NOT SOUND – NOT JUSTIFIED, NOT EFFECTIVE, IS NOT CONSISTENT WITH NATIONAL PLANNING POLICY.
These representations are submitted by Quy Tech Ltd, on behalf of the landowners, and are made with reference to a potential employment land allocation at Quy Tech, a 165-ha site in Stow-cum-Quy.
The Site is promoted for the development of a campus based mid-tech employment facility, not only providing important contemporary employment floorspace but bespoke ancillary housing needed to serve the employment uses and additional complementary facilities. All with the wider ability to be self-powered by the site’s own solar farm.
East Cambridge is a clear direction of travel for growth in Greater Cambridge. The failure to recognise the east of Cambridge as a wider gateway opportunity, with the necessary infrastructure and connectivity already in place, to sustain greater levels of economic and residential growth represents a wasted opportunity.
This Site is just 250m north of the Cambridge East allocation and ideally located to connect into and complement the new development at Marleigh and that proposed for Cambridge Airport. In terms of wider connectivity, the Site has direct access to the A14, whilst the Cambridge East development, Newmarket Road travel hub and Cambridge North are all directly accessible from the Site by standalone foot and cycle routes.
These representations are accompanied by an Economic Assessment (hereby submitted) of the economic aspirations of the draft Greater Cambridge Local Plan. This concludes that:
• The need for employment, and especially knowledge-intensive employment, is much greater than that identified and allocated for in the draft Local Plan.
• The identified needs do not reflect new and emerging trends.
• The conclusions drawn are primarily quantitative i.e. simple floorspace figures, without qualitative assessment of the location, nature and setting of accommodation needed. Fundamentally, this work fails to recognise the growing need for campus based contemporary commercial floorspace.
A Vision Document (hereby submitted) for the Site also accompanies these representations. The document sets out how proposals for the Site can come forward and the strength of connectivity to the Cambridge East development i.e. Marleigh and the proposals for the airport, the nearby Newmarket Road Travel Hub and Cambridge North train station.
A Cambridge Green Belt Assessment was published to accompany the initial Local Plan proposals in 2021. An update to this study, the ‘Greater Cambridge Green Belt Assessment Review’ has been issued in 2026, following changes to National Policy and Guidance.
In response to the main issues raised in representations to the Reg 18 Draft Local Plan the Council has confirmed that:
‘The study confirms that the long established Cambridge Green Belt purposes provide a locally-specific application of the NPPF purposes, delivering a more helpful structure for the analysis of variations in the role of Green Belt land than provided by the more generic NPPF purposes. The city has a Green Belt because of its historic character and all three Cambridge purposes form elements of NPPF Purpose D. The Study also considers how grey belt should be applied in a Cambridge context. It reviews parcel by parcel contribution to Green Belt purposes, highlighting areas that could provisionally be considered as grey belt where they do not make a strong contribution to Green Belt purposes.
Paragraph 146 of the NPPF establishes that where it is necessary to release Green Belt land for development, plans should give priority to previously developed land, then consider grey belt which is not previously developed, and then other Green Belt locations. The plan making process has not identified exceptional circumstances for Green Belt release to meet general needs. As such, the identification of the location of grey belt land within Greater Cambridge does not affect the Councils’ position regarding the identified preferred development strategy.’
In this context, draft Policy S/GB continues to states that the intention that the Green Belt will be maintained around Cambridge with the specific purpose to:
a. Preserve the unique character of Cambridge as a compact, dynamic city, with a thriving historic centre
b. Maintain and enhance the quality of its setting; and
c. Prevent communities in the environs of Cambridge from merging into one another and with the City.
We maintain our objection to draft Policy S/GB: The Cambridge Green Belt, on the basis that none of these purposes are as listed at paragraph 143 of the NPPF.
The Council’s response to representations to Reg 18 is that all three of the proposed are ground in NPPF purpose D. This is not correct as arguably only grounds ‘a’ and ‘b’ fall within purpose D. Having regard to the merging of places paragraph 143 makes it clear that the purpose of the Green Belt is ‘specifically to prevent neighbouring towns merging into one another’ as opposed to ‘communities in the environs…’.
It remains unclear why the Cambridge Local Plan should seek to consider its Green Belt, and consequently review development proposals, against different criteria to that set out in the NPPF.
It is notable that the policy does not reference Grey Belt, nor does the policy allow for any consideration of need or Green Belt review over the plan period. Having regard to the Council’s response to Reg 18 representations the identification of Grey Belt does not require exceptional circumstances but rather a review of the contribution of that piece of Green Belt in the context of unmet need.
We are extremely concerned that the economic forecasts of the draft Greater Cambridge Local Plan are not as ambitious as they should be and do not match up to the Government’s aspirations for the area. As a result, too few sites are allocated for employment development. Equally, Policy S/DS: Development Strategy makes clear that sites on the edge of Cambridge are to be prioritised for housing and employment development, outside of the Cambridge Urban Area. In this context further release of green belt, to facilitate opportunities such as Quy Tech, needs to be considered to meet this need.
The NPPF (December 2024) defines Grey Belt as land in the Green Belt that does not strongly contribute to any of the purposes (a) to check the unrestricted sprawl of large built up areas, (b) to prevent the neighbouring towns merging into one another or (d) to preserve the setting and special character of historic towns, listed at paragraph 143.
The Greater Cambridge Green Belt Assessment (August 2021) makes clear that the Quy Tech Site is closely associated with the settlement of Stow-cum-Quy. It is not clear why the promotion of land at Quy Tech has not been assessed in detail within the 2026 Green Belt review, notwithstanding it is evident that the conclusions drawn in relation to Quy Tech in 2021 have not been updated.
In this context, the Quy Tech opportunity is considered below having regard to Grey Belt considerations:
• To check the unrestricted sprawl of large built up areas: to the east the urban area of Cambridge is restricted by farmland and the A14 beyond. Whilst benefiting from strong connectivity to the east of Cambridge generally Quy Tech would operate as a standalone campus facility associated with Stow-cum-Quy. Development of the Site would not visually read as the sprawl of the Cambridge Urban Area.
• To prevent the neighbouring towns merging into one another: the development of this Site would not lead to the merging of neighbouring towns. Cambridge is identified at the top of the settlement hierarchy, whilst Stow-cum-Quy is identified as a 6th (lowest tier) ‘Infill Village’ in the draft Local Plan. Notwithstanding this, Cambridge is bordered by agricultural field, the A14 is between the two Sites and further landscape buffers would be designed into the campus itself. Development of the Quy Tech Site would not read as a continuation of the Cambridge Urban Area.
• To preserve the setting and special character of historic towns: Development of the Site would not impact the historic setting of Cambridge. As is identified in the Greater Cambridge Green Belt Assessment (2021) the land is not close enough to the main urban area of Cambridge to be associated with it.
Having regard to Policy S/GB: The Cambridge Green Belt, it is not considered that the Site contributes significantly to any of the three stated purposes.
Relative to the consideration of the impact on the Green Belt at Quy Tech is the ability to expand any existing large-scale research and development sites within Greater Cambridge to meet the need for additional mid-tech floorspace. The Green Belt implications of any such proposal is considered in the context of draft Policy S/GB below:
• Cambridge Biomedical Campus: The site is not considered Grey Belt and further expansion to the west would have significant impact on the setting of Cambridge, whilst we consider that expansion to the east would also result in moderate to relatively significant impact.
• Babraham Research Campus: Whilst this site may have Grey Belt credentials expansion of the campus would, we consider, have moderate to relatively significant impact on Cambridge’s setting.
• Cambridge Science Park: The Site is not considered grey belt. Development of the Site would have significant impact on the unique character of Cambridge whilst also having moderate impact on Cambridge’s setting.
• Peterhouse Technology Park: The site is not considered grey belt. Development of the site would have a relatively significant to significant impact on the unique character of Cambridge whilst also having a relatively significant impact on the quality of Cambridge’s setting.
• St John’s Innovation Centre: Green Belt considerations are not applicable, but the site is subject to other constraints.
• Wellcome Genome Campus: Outside of the Green Belt
• Melbourn Science Park: Outside of the Green Belt
• Granta Park: Outside of The Green Belt
It is clear then that all sites in close proximity to Cambridge require Green Belt release to meet additional need for employment floorspace. Of these the opportunity at Quy Tech presents the least impact in terms of loss of sensitive Green Belt land.
We object to Policy S/GB: The Cambridge Green Belt, and find it unsound, on the basis that further green belt release is required to meet additional need for employment floorspace. It is recommended that the removal of the Quy Tech Site from the Green Belt should be considered in this context.