Full text:
Argues that Policy S/DS and the wider development strategy are unsound, inflexible and inconsistent with national policy. It contends that the Plan relies excessively on large strategic sites with unrealistic delivery assumptions, improperly includes windfall housing within the first five years, and uses the Liverpool method to defer housing shortfalls. The strategy fails to allocate new rural or small and medium-sized housing sites, despite national policy support and local affordability needs. It also underutilises suitable Grey Belt land, limits housing choice, and risks worsening affordability, particularly in sustainable settlements such as Histon and Impington.
Whilst in principle we do not object to the delivery of a large number of new homes at scale as set out in
Policy S/DS. We consider that the overall approach is unsound and inconsistent with national policy as we
set out below.
The speed at which these large, strategic developments (ie: North Cambourne and Grange Farm) can
deliver homes is often far slower than the Council has envisaged historically. A review of historic Annual
Monitoring Reports demonstrates that whilst some of the large strategic sites in the current Development
Plan, may now be delivering at an appropriate rate, most sites came on stream several years later than
anticipated, did not deliver as quickly once the first completions were achieved, and many still deliver less
homes year on year than planned for.
As a result of the chosen development strategy, we have the following comments to make that demonstrate
it is unsound:
There are several sites identified in the Council’s Housing Delivery Study Addendum 2026 Update
that assumes they will consistently deliver 300 – 350 homes per annum over the Plan, which is
highly unrealistic. Whilst on strategic sites this might be achieved for short periods, it is not the
case that this is consistently achieved in any evidenced way. In fact, Lichfield’s Start to Finish at
Appendix 2 considers sites of greater than 3,500 homes and provides evidence as to how the
Council’s approach is inappropriate.
- Windfalls have been included in the deliverable supply for years 1 – 5, contrary to the Framework
and PPG.
- The ‘lumping’ together of rural centres, minor rural centres, group villages and infill villages from
the settlement hierarchy (taken from Policy S/SH), as the locations with the lowest preference to
deliver jobs and homes, clearly fails to distinguish between what may be highly sustainable
locations in the rural area (ie: Histon and Impington) a Rural Centre-the highest of these categories
(where there will be no limit on scheme size), and which is clearly capable of delivering an
appropriate scale of development (ie: up to 50 dwelling sized sites as encouraged in the adopted
Neighbourhood Plan).
- The proposed use of the Liverpool method to address historical backlog or shortfall in housing
delivery is contrary to the preferred approach in PPG which explains that any shortfall should
accrue from the base-date of a plan and added to the five-year requirement (Sedgefield approach).
Whilst the PPG does allow the use of the Liverpool method it adds that this must be justified during
the plan-making process. The Council’s own evidence base states they consider a five-year land
supply can be demonstrated under Sedgefield and resultingly there is no need to use the Liverpool
method which suppresses housing delivery and therefore runs contrary to the government’s
ambition to significantly boost house building.
In taking such an approach, there is not sufficient flexibility or robustness in the development strategy.
The Council has not identified any new allocations for housing in the rural area which fails to support the
vitality of the rural area and existing settlements (paragraphs 82 and 83 of the Framework). We believe
that this decision, has been made in part, to avoid development in the Green Belt, and therefore fails to
strike a more balanced approach to housing delivery and mix of housing across the Plan period.
Small and Medium Sized Sites
Small and medium sites such as this Site are key to a far more balance approach to housing. Paragraph
73 of the NPPF (December 2024) identifies that small and medium sized sites can make an important
contribution to meeting the housing requirement of an area. They are also essential for small and medium
enterprise housebuilders to deliver new homes whilst being built out relatively quickly.
The Plan does not propose to allocate any new housing sites to address this requirement, essentially
because they consider:
- It is challenging to identify a large number of small sites to meet the 10% requirement.
- It would be considered to undermine the Council’s development strategy and necessitates the
release of Green Belt sites conflicting with the aim of protecting the Cambridge Green Belt as the
larger and better served villages are located within the Green Belt.
We have two concerns with this approach which need to be considered and addressed by the next iteration
of the plan.
A final point of note; whilst the Site is larger than 2.5ha and therefore exceeds the 2.5ha site area set in
the NPPF for small sites, the Site area can easily be reduced slightly to meet the threshold without
undermining the ability to deliver housing in this location.
Green Belt / Grey Belt
We welcome the Council’s now reviewing the potential for Grey Belt sites, though still do not believe that
this review has been appropriately considered as a development strategy through the Sustainability
Appraisal.
The Site has been identified as a Grey Belt site under reference HI12 in the Green Belt Review, with
development having low harm and the Site’s weak Purpose D contribution. It is therefore clear that the
Site is well placed to deliver homes to meet the identified increased need for new homes as part of a more
balanced development strategy, and its release could be considered high up the Green Belt release
hierarchy as set out in paragraph 148 for the Framework.
Windfall
PPG (3-023) states that a windfall allowance forms part of the broad locations for growth which can be
relied upon for years 6-15 rather than part of the specific sites which can be relied upon in years 1-5.
Windfall allowance by its very nature does not comprise specific sites which are all that can be included
as part of the deliverable supply in years 1-5 according to paragraph 72 of the NPPF.
The Housing Delivery Study Addendum 2026 Update however includes a windfall allowance of 1,562
homes in the period 2028-33 contrary to national policy and guidance. Without this the Housing Delivery
Study Addendum 2026 Update identifies a plan period supply of 50,470 homes. This alone results in a
headroom of just 5% over the plan period against the proposed insufficient housing requirement, which
compounds the insufficiency of supply. This is even without our significant concerns raised above
regarding delivery rates applied to strategic sites.
Relying upon windfall development to address as much of the 10% requirement as possible, does not help
provide small and medium enterprise housebuilders with the certainty required to invest in delivering sites.
Across Greater Cambridge there has also been a general decline in the delivery of windfall sites over the
years.
The Greater Cambridge Housing Delivery Study Addendum3 in section 2 considers windfall delivery
between 2006 and 2024 and considers a windfall allowance of 425 dwellings per annum would be robust.
This section of the report sets out what it considers a favourable policy which may assist the delivery of
windfall sites in the future. However, it fails to identify why over time there has been a general trend
downward on windfall sites, and whether in reality, particularly in the South Cambridgeshire area there is
now a lack of available sites to continue to deliver windfall at scale across the plan period.
For instance, it presents a data set as far back as 2006 – 2007 for windfall completions to find an average
delivery rate of 470 dwellings per annum, fails to realise that Greater Cambridge has not delivered more
than 470 dwellings in a year from windfall since 2016 – 2017. Even if the Council uses 425 dwellings per
annum for windfall over the previous seven years of data the average delivery has been 395 dwellings per
annum.
As such, there needs to be greater certainty injected into small and medium sized sites by allocating these
in the emerging Local Plan, to aid with confidence of being able to deliver such sites but also recognising that opportunities for brownfield redevelopment or residential sub-division can only continue to deliver so
much housing across Greater Cambridge.
Vitality of the Rural Area
The Council suggests at 2.42 that allocations in the Rural Area would result in an overreliance on the
private motor vehicle. However, this position overlooks several important factors:
- The spatial strategy proposed by the Council does not consider the unique characteristic of each
of the settlements in the rural area individually, and their ability to grow to support the vitality of
settlements and the viability of their services. This is a consequence of effectively grouping the
whole rural area into one pot within Policy S/DS.
- The Council, as far as we can see, has not revisited their stance on releasing Green Belt in the
villages, which they state they are ‘protecting’ despite several sites, including this one, now being
designated as Grey Belt.
- Expanding the rural settlements would lead to increased viability / opportunities to improve
sustainable transport opportunities (paragraphs 82 and 83 of the Framework).
- Whilst the Council does not readily allocate any new developments at the rural settlements, it is
clear that the Council does not view all settlements in the rural area as being unsustainable. For
instance, Policy S/SH – Settlement Hierarchy does not set a limit of the size of residential
development within the defined extent of Rural Centres such as Histon and Impington subject to
demonstrating adequate services and facilities exist.
- Some Rural Centres such as Impington and Histon are actually closer and as well served as the
city in terms of access to large employment centres (ie: Science Park).
Policy S/SH effectively creates a juxtaposition whereby it is recognised that growth within Histon and
Impington need not be constrained as it benefits from a high level of services, facilities and accessibility to
the main urban area; yet in failing to allocate any sites, growth is basically constrained to the settlement
boundaries where windfall opportunities are already restricted.
Failing to offer sufficient choice and flexibility
The focus upon large new settlements, urban redevelopment and SUEs fails to properly consider the need
to offer sufficient choice and flexibility to prospective homeowners. Not all prospective purchasers will be
able to, or wish to buy, in these locations. For instance, existing young residents of Histon and Impington
may wish to buy a home in the settlement to be close to existing family for childcare which may not be
possible should they have to move to other proposed allocations.
Local Housing Need
The adopted neighbourhood plan encourages sites of up to 50 dwellings and finds:
• That the third most important matter to local residents was the affordability of housing.
• The supply of affordable housing was considered the second most important in terms of need for
improvement.
Despite this both the neighbourhood plan and emerging Local Plan fail to identify housing sites to meet
the identified local need. Rather, it puts the onus entirely on windfall sites and exceptions sites which carry
high risk for developers and therefore are not likely to come forward at scale. Additionally, windfall sites
within the settlement not delivering 10 or more dwellings will not be required to deliver any affordable
housing.
The proposed development strategy will only exacerbate the affordability issue in Histon and Impington,
likely pushing young people out of their local communities away from their support networks. This may also exacerbate the car dependence concerns the Council has by pushing these people further from
Cambridge to seek cheaper housing in less well served areas (ie: rural East Cambridgeshire).
The Neighbourhood Plan also identifies that Histon and Impington’s existing housing mix is:
● Made up of relatively high proportions of larger family houses
● Has comparatively limited provision of smaller homes
● Has a reliance on South Cambridgeshire's affordable housing evidence to identify affordable housing
needs.
Whilst in principle we do not object to the delivery of a large number of new homes at scale as set out in Policy S/DS. We consider that the overall approach is unsound and inconsistent with national policy as we set out below.
The speed at which these large, strategic developments (ie: North Cambourne and Grange Farm) can deliver homes is often far slower than the Council has envisaged historically. A review of historic Annual Monitoring Reports demonstrates that whilst some of the large strategic sites in the current Development Plan, may now be delivering at an appropriate rate, most sites came on stream several years later than anticipated, did not deliver as quickly once the first completions were achieved, and many still deliver less homes year on year than planned for.
As a result of the chosen development strategy, we have the following comments to make that demonstrate it is unsound:
- There are several sites identified in the Council’s Housing Delivery Study Addendum 2026 Update that assumes they will consistently deliver 300 – 350 homes per annum over the Plan, which is highly unrealistic. Whilst on strategic sites this might be achieved for short periods, it is not the case that this is consistently achieved in any evidenced way. In fact, Lichfield’s Start to Finish at Appendix 2 considers sites of greater than 3,500 homes and provides evidence as to how the Council’s approach is inappropriate.
- Windfalls have been included in the deliverable supply for years 1 – 5, contrary to the Framework and PPG.
- The ‘lumping’ together of rural centres, minor rural centres, group villages and infill villages from the settlement hierarchy (taken from Policy S/SH), as the locations with the lowest preference to deliver jobs and homes, clearly fails to distinguish between what may be highly sustainable locations in the rural area (ie: Histon and Impington) a Rural Centre-the highest of these categories (where there will be no limit on scheme size), and which is clearly capable of delivering an appropriate scale of development (ie: up to 50 dwelling sized sites as encouraged in the adopted Neighbourhood Plan).
- The proposed use of the Liverpool method to address historical backlog or shortfall in housing delivery is contrary to the preferred approach in PPG which explains that any shortfall should accrue from the base-date of a plan and added to the five-year requirement (Sedgefield approach). Whilst the PPG does allow the use of the Liverpool method it adds that this must be justified during the plan-making process. The Council’s own evidence base states they consider a five-year land supply can be demonstrated under Sedgefield and resultingly there is no need to use the Liverpool method which suppresses housing delivery and therefore runs contrary to the government’s ambition to significantly boost house building.
In taking such an approach, there is not sufficient flexibility or robustness in the development strategy.
The Council has not identified any new allocations for housing in the rural area which fails to support the vitality of the rural area and existing settlements (paragraphs 82 and 83 of the Framework). We believe that this decision, has been made in part, to avoid development in the Green Belt, and therefore fails to strike a more balanced approach to housing delivery and mix of housing across the Plan period.
Small and Medium Sized Sites
Small and medium sites such as this Site are key to a far more balance approach to housing. Paragraph 73 of the NPPF (December 2024) identifies that small and medium sized sites can make an important contribution to meeting the housing requirement of an area. They are also essential for small and medium enterprise housebuilders to deliver new homes whilst being built out relatively quickly.
The Plan does not propose to allocate any new housing sites to address this requirement, essentially because they consider:
- It is challenging to identify a large number of small sites to meet the 10% requirement.
- It would be considered to undermine the Council’s development strategy and necessitates the release of Green Belt sites conflicting with the aim of protecting the Cambridge Green Belt as the larger and better served villages are located within the Green Belt.
We have two concerns with this approach which need to be considered and addressed by the next iteration of the plan.
A final point of note; whilst the Site is larger than 2.5ha and therefore exceeds the 2.5ha site area set in the NPPF for small sites, the Site area can easily be reduced slightly to meet the threshold without undermining the ability to deliver housing in this location.
Green Belt / Grey Belt
We welcome the Council’s now reviewing the potential for Grey Belt sites, though still do not believe that this review has been appropriately considered as a development strategy through the Sustainability Appraisal.
The Site has been identified as a Grey Belt site under reference HI12 in the Green Belt Review, with development having low harm and the Site’s weak Purpose D contribution. It is therefore clear that the Site is well placed to deliver homes to meet the identified increased need for new homes as part of a more balanced development strategy, and its release could be considered high up the Green Belt release hierarchy as set out in paragraph 148 for the Framework.
Windfall
PPG (3-023) states that a windfall allowance forms part of the broad locations for growth which can be relied upon for years 6-15 rather than part of the specific sites which can be relied upon in years 1-5. Windfall allowance by its very nature does not comprise specific sites which are all that can be included as part of the deliverable supply in years 1-5 according to paragraph 72 of the NPPF.
The Housing Delivery Study Addendum 2026 Update however includes a windfall allowance of 1,562 homes in the period 2028-33 contrary to national policy and guidance. Without this the Housing Delivery Study Addendum 2026 Update identifies a plan period supply of 50,470 homes. This alone results in a headroom of just 5% over the plan period against the proposed insufficient housing requirement, which compounds the insufficiency of supply. This is even without our significant concerns raised above regarding delivery rates applied to strategic sites.
Relying upon windfall development to address as much of the 10% requirement as possible, does not help provide small and medium enterprise housebuilders with the certainty required to invest in delivering sites. Across Greater Cambridge there has also been a general decline in the delivery of windfall sites over the years.
The Greater Cambridge Housing Delivery Study Addendum in section 2 considers windfall delivery between 2006 and 2024 and considers a windfall allowance of 425 dwellings per annum would be robust.
This section of the report sets out what it considers a favourable policy which may assist the delivery of windfall sites in the future. However, it fails to identify why over time there has been a general trend downward on windfall sites, and whether in reality, particularly in the South Cambridgeshire area there is now a lack of available sites to continue to deliver windfall at scale across the plan period.
For instance, it presents a data set as far back as 2006 – 2007 for windfall completions to find an average delivery rate of 470 dwellings per annum, fails to realise that Greater Cambridge has not delivered more than 470 dwellings in a year from windfall since 2016 – 2017. Even if the Council uses 425 dwellings per annum for windfall over the previous seven years of data the average delivery has been 395 dwellings per annum.
As such, there needs to be greater certainty injected into small and medium sized sites by allocating these in the emerging Local Plan, to aid with confidence of being able to deliver such sites but also recognising that opportunities for brownfield redevelopment or residential sub-division can only continue to deliver so much housing across Greater Cambridge.
Vitality of the Rural Area
The Council suggests at 2.42 that allocations in the Rural Area would result in an overreliance on the private motor vehicle. However, this position overlooks several important factors:
- The spatial strategy proposed by the Council does not consider the unique characteristic of each of the settlements in the rural area individually, and their ability to grow to support the vitality of settlements and the viability of their services. This is a consequence of effectively grouping the whole rural area into one pot within Policy S/DS.
- The Council, as far as we can see, has not revisited their stance on releasing Green Belt in the villages, which they state they are ‘protecting’ despite several sites, including this one, now being designated as Grey Belt.
- Expanding the rural settlements would lead to increased viability / opportunities to improve sustainable transport opportunities (paragraphs 82 and 83 of the Framework).
- Whilst the Council does not readily allocate any new developments at the rural settlements, it is clear that the Council does not view all settlements in the rural area as being unsustainable. For instance, Policy S/SH – Settlement Hierarchy does not set a limit of the size of residential development within the defined extent of Rural Centres such as Histon and Impington subject to demonstrating adequate services and facilities exist.
- Some Rural Centres such as Impington and Histon are actually closer and as well served as the city in terms of access to large employment centres (ie: Science Park).
Policy S/SH effectively creates a juxtaposition whereby it is recognised that growth within Histon and Impington need not be constrained as it benefits from a high level of services, facilities and accessibility to the main urban area; yet in failing to allocate any sites, growth is basically constrained to the settlement boundaries where windfall opportunities are already restricted.
Failing to offer sufficient choice and flexibility
The focus upon large new settlements, urban redevelopment and SUEs fails to properly consider the need to offer sufficient choice and flexibility to prospective homeowners. Not all prospective purchasers will be able to, or wish to buy, in these locations. For instance, existing young residents of Histon and Impington may wish to buy a home in the settlement to be close to existing family for childcare which may not be possible should they have to move to other proposed allocations.
Local Housing Need
The adopted neighbourhood plan encourages sites of up to 50 dwellings and finds:
• That the third most important matter to local residents was the affordability of housing.
• The supply of affordable housing was considered the second most important in terms of need for improvement.
Despite this both the neighbourhood plan and emerging Local Plan fail to identify housing sites to meet the identified local need. Rather, it puts the onus entirely on windfall sites and exceptions sites which carry high risk for developers and therefore are not likely to come forward at scale. Additionally, windfall sites within the settlement not delivering 10 or more dwellings will not be required to deliver any affordable housing.
The proposed development strategy will only exacerbate the affordability issue in Histon and Impington, likely pushing young people out of their local communities away from their support networks. This may also exacerbate the car dependence concerns the Council has by pushing these people further from Cambridge to seek cheaper housing in less well served areas (ie: rural East Cambridgeshire).
The Neighbourhood Plan also identifies that Histon and Impington’s existing housing mix is:
● Made up of relatively high proportions of larger family houses
● Has comparatively limited provision of smaller homes
● Has a reliance on South Cambridgeshire's affordable housing evidence to identify affordable housing needs.