Appendix B: Assessment of Sites included in the Greater Cambridge Housing Trajectory - Unallocated Sites with Resolution to Grant Planning Permission
Showing comments and forms 1 to 1 of 1
Comment
Greater Cambridge Housing Trajectory and Five Year Housing Land Supply - Main Document
Representation ID: 168397
Received: 14/10/2019
Respondent: Cambourne Town Council
Representation Summary:
There is reference to developments on unallocated sites with a resolution to grant planning permission being included in the supply. This is contrary to several recent appeal decisions (e.g. Bures Hamlet ref: 3207509 and Woolpit ref: 3194926) that make clear permissions issued after the base date should not be counted (including sites subject to a resolution to grant at the base date). There does not appear to be any reliance in the forecast supply on such sites and it is unclear why this reference is included as it simply serves to open up the Council's methodology to criticism.